Santos happy as GLNG project remains on track for 2015

The GLNG project on Gladstone's Curtis Island is 45% complete.
The GLNG project on Gladstone's Curtis Island is 45% complete.

THE Santos-led GLNG project is now 45% complete and remains on track for first LNG in 2015.

Santos chief executive officer David Knox said construction on the Gladstone project was pleasing.

In Santos' fourth quarter report released on Thursday, Mr Knox said a significant milestone had been achieved for the GLNG underground gas transmission pipeline with the arrival of the last shipment of pipe in Queensland, and the start of pipeline burial.

All 420km of pipe for the gas transmission pipeline has been delivered to pipe yards in Gladstone and Port Alma.

A total of 108km of the mainland pipeline right-of-way has been cleared and graded, with 94km of pipe strung and 35km of pipe welded.

In December, pipeline burial in the Arcadia Valley began, which is the final step before rehabilitation works are carried out, the report said.

For the marine crossing, sealing of the access track started, and site pad and launch shaft preparation is continuing.

A tunnelling machine is being commissioned in Brisbane, and tunnel concrete segment moulds have been prepared. Segment fabrication began in early January.

On Curtis Island, construction of the two LNG trains and supporting infrastructure continues to progress.

Concrete wall lifts are underway for both LNG tanks, erection and welding of the temporary outer support brackets for the steel roof of LNG tank B has been completed and installation of roof plates has begun.

Sanctioned in January 2011, GLNG includes the development of CSG resources in the Bowen and Surat Basins in south-east Queensland, construction of a 420km underground gas transmission pipeline to Gladstone, and two LNG trains with a combined nameplate capacity of 7.8mtpa on Curtis Island.

The project has an estimated gross capital cost of US$18.5 billion from final investment decision to the end of 2015.

Topics:  curtis island, gladstone, glng, lng, mining, resources, santos




Weather: Is our winter back on the Fraser Coast?

SUNSHINE: Irish visitor Dualta Mitchell-Higgins, 11, puts the finishing touches to the sandcastle he spent two hours building on Torquay Beach. He is pictured with his dad's girlfriend Erica Johnston.

Last week we had unseasonably high temps

What’s left of Hervey Bay’s drive-in theatre

NOSTALGIA: The film reels have stopped, the sound has died and the crowds long gone ... the old drive-in theatre at Scrub Hill on the Hervey Bay Maryborough Rd.

The Fraser Coast Regional Council owns the now run-down theatre

Latest deals and offers

Three reasons your mind will be blown this week

Alan Dale and Jacki Weaver in a scene from the TV series Secret City.

THREE shows on Foxtel to make your mind boggle.

Elena wins MasterChef: “I’m ecstatic and eager to celebrate"

MasterChef Australia 2016 winner Elena Duggan, from Noosa.

NOOSA chefs survive marathon grand final dish by Heston Blumenthal.

Shannen Doherty shaves hair during cancer battle

Shannen Doherty has completely shaved off her hair

Brian McFadden makes daughters pay for own Christmas gifts

McFadden makes his daughters pay for half their presents

Lady Gaga is a godmother

Lady Gaga has become a godmother to her friends' daughter

You can own this Queensland town for just $1

Yelarbon

Unprecedented auction of town's business centre with no reserve

Work starts on $15M Caloundra apartment building

Turning the first sod at the Aqua View Apartments site in Kings Beach are (from left) husband-and-wife developers Alex Yuan and Stella Sun with construction company Tomkins director Mike Tomkins and Councillor Tim Dwyer.

Developers excited about addition to Kings Beach skyline

72-year-old Coast developer set to start new project

GREEN LIGHT: The Cosmopolitan has been approved for development at Cotton Tree.

Meet the Canberran set to deliver another chapter for Coast suburb

Plans revealed for 1500-lot 'master-planned community'

Precinct will be bounded by Boundary St and Shoesmith Rd

Ecco Ripley sales run sparks prime release

MOVING IN: Sekisui House has announced the release of more residential blocks at Ecco Ripley.

Sekisui House is preparing to unveil more land at Ecco Ripley

The climb is slow but property on the way up

Michael Matusik, director of Matusik Property Insights.Photo Allan Reinikka / The Morning Bulletin

The improvement would be mild when compared to past cycles