Centro investors may walk away

INVESTORS behind the proposed second stage of Hervey Bay's Centro complex are set to ditch the $100m expansion project after years of trying to get approvals.

For more than five years Centro Hervey Bay has been trying to get major development plans through the council.

Alistair Brightman

INVESTORS behind the proposed second stage of Hervey Bay’s Centro complex are set to walk away from the $100 million expansion project after more than five years of frustration trying to get approvals.

While initial development applications for improvements were lodged in 2004, Leda Group, the investors and owners of Centro, claim the council has continued to put obstacle after obstacle in front of them.

In the latest block to the proposal it’s believed the council has asked Leda to pay a $1.1 million public art levy, build a $1 million mobility corridor and contribute $1 million to roads.

The council is also asking Leda to give up its land and build a road on its site. In essence it means that the new approval conditions will cost Leda an extra $3 million on top of what it is already paying the council.

The situation has got to the point where Leda has asked Mayor Mick Kruger for a crisis meeting to try to find a way through the tangled web of red tape the council has placed and continues to place on the project.

It’s believed the Leda Group is particularly concerned about the input the council’s town planner, David King, has had in the project.

Sources close to Leda say Mr King’s involvement has been one of the major hurdles to getting the project up and running.

Most importantly the sources say that had the council’s promises of early approval been forthcoming the second stage of Centro would have already been built and in operation.

They now claim the Leda group has lost total confidence in the Fraser Coast Regional Council and they believe the council does not appreciate the benefits that the $100 million project will bring to the district.

These benefits, they claim, will include supplying 1000 construction jobs as well as 900 permanent and 714 multiplier effect jobs to the region.

The Chronicle’s sources say that Leda is ready to put the project on hold after labelling it as economically unviable because of the conditions currently imposed on it by the council.

The sources say that Leda is prepared to pay reasonable levies but the latest ask by the council is in “fairyland”.

 
Fraser Coast Chronicle  
 
  • Mostly sunny

    Today

    Mostly sunny

    11°C/28°C
  • Possible shower

    Tomorrow

    Possible shower

    13°C/26°C

Fraser Coast forecast »

Special offers
Virgo

24 August - 23 September

You're probably worried about what someone's NOT saying whether it be a personal or professional problem on their part. Perhaps they have a health matter they're... More Horoscopes »

Select your zodiac sign

Aries | Taurus | Gemini | Cancer | Leo | Virgo | Libra | Scorpio | Sagittarius | Capricorn | Aquarius | Pisces

What's On

Browse

 

powered by

Link to top
APN news and media

© APN News & Media Ltd 2010. Unauthorised reproduction is prohibited under the laws of Australia and by international treaty. APN | APN Group Websites

Back to access links