Hervey Bay pool refurbishment cost blows out to $1 million

THE cost of the Hervey Bay pool refurbishment has blown out to $1 million because a new concrete shell had to be poured over the existing shell.

The original cost of the Hervey Bay Aquatic Centre was $780,000 and included removing the old fibreglass surfacing and relining the entire pool with pebblecrete.

Councillor Darren Everard said the end wall of the pool would be removed to ensure it was still 50m and the planned finish date for the project was November.



Thieves spotting easy steals on Fraser Coast

premium_icon Thieves spotting easy steals on Fraser Coast

Since July more than 50 vehicles across the region have been stolen

Cash splash at Coast hotels for school holidays

premium_icon Cash splash at Coast hotels for school holidays

Tourists are seeing what the Fraser Coast has to offer.

Drug driver jailed

premium_icon Drug driver jailed

He tested positive when intercepted by police.

Local Partners