NEARLY FINISHED: Santos GLNG’s newly constructed 4.3km tunnel underneath The Narrows is cleaned and prepared for the installation of the gas transmission pipeline.
NEARLY FINISHED: Santos GLNG’s newly constructed 4.3km tunnel underneath The Narrows is cleaned and prepared for the installation of the gas transmission pipeline. Contributed

GLNG's 420km gas transmission project in its final stages

GLNG's pipeline is weeks away from completion, with the final stages of construction set to see the pipeline pushed through the under-sea tunnel at The Narrows just north of Gladstone.

The tunnel, which links the pipeline route with Curtis Island, has been filled with sea water to buoy the 42-inch diameter pipe as it is pushed through.

It is expected to take up to four weeks for about 120 segments of pipeline, each measuring 36m in length, to be welded together and pushed through the tunnel using a large hydraulic jack.

With the 420km gas transmission project in its final stages, Santos vice president downstream GLNG Rod Duke said the under-sea tunnel was a feat in itself, and was completed last month without disturbance to the local marine environment and with minimal impact to the surrounding coastal environments.

The 3.45m internal diameter tunnel is about eight metres below the sea bed.

The gas transmission pipeline is being built by contractor Saipem Australia, and the tunnel was constructed by subcontractor Thiess.

Joint Venture

GLNG partners:

  • Santos
  • Petronas
  • Total
  • Kogas


Why was this idiot driving?

premium_icon Why was this idiot driving?

Driver accused of killing grandmother just released on parole

Qld weather: Little reprieve as flood warnings put in place

Qld weather: Little reprieve as flood warnings put in place

Brisbane weather: Queensland storms to bring ‘month’s worth of rain

M'boro man tells of moment car was swept off Bay road

M'boro man tells of moment car was swept off Bay road

He was returning home from Hervey Bay Airport when it happened.

Local Partners